Item Title:Public Works - Construction of the Ascarate special event area improvements (Contract No. 2020-0261)
Submitted By:Norma Rivera Palacios, Executive Director, Public Works Department (915) 546-2015
Subject:Approve and authorize the County Judge to sign the Construction Contract Between Owner and Contractor with Jordan Foster Construction, LLC for the construction of the Ascarate special event area and improvements in the amount of $435,114. Funding is available in CP-CPASCPKIM07-PARK IMPROV, GF-ASCARATE-CAP OUT-PARK IMPRO, CP-REPLACE20-PARK IMPROV. (Contract No. 2020-0261)
Background:On September 17, 2018 Commissioners Court approved the relocation of funds for park projects identified in the approved County Regional Park Plan.  The Ascarate Park special event area improvements include asphalt trails, irrigated flat fields and multi-purpose concrete courts
Fiscal Impact:

$435,114

Funding available in:

CP-CPASCPKIM07-PARK IMPROV - $311,719

COCP-3004-ASCIM07-431-80-80000-00000-703003-

 

GF-ASCARATE-CAP OUT-PARK IMPRO - $73,395

COGF-1000-0000000-431-70-70101-0001-00000-703003-

 

CP-REPLACE20-PARK IMPROV- $50,000

COCP-3001-REPLC20-431-70-70000-0415-PKIMP-703003-

Recommendation:Approve and authorize the County Judge to sign the Construction Contract Between Owner and Contractor with Jordan Foster Construction, LLC for the construction of the Ascarate special event area and improvements in the amount of $435,114. Funding is available in CP-CPASCPKIM07-PARK IMPROV, GF-ASCARATE-CAP OUT-PARK IMPRO, CP--REPLACE20-PARK IMPROV. (Contract No. 2020-0261)
Prior Action:

October 19, 2020 (Item 14) – Region 19 Job Order Contract (JOC) 17-7261 awarded to Jordan Foster Construction of El Paso

 

September 17, 2018 (Item 18) – Public Works -Reallocation CP07 Park funds for projects

 

August 6, 2018 (Item 21) – Public Works - County Regional Park Plan approved 

Strategic Plan:..
Strategic Plan Information:

ATTACHMENTS:
DescriptionUpload Date
20-0261 Fixed Price Construction Contract- Ascarate Park Special Events Area Improvements- Jordan Foster- 10.22.20 FINAL10/22/2020
CA Apprvoal 2020-026110/21/2020