Subject:Approve and authorize the County Judge to sign the Final Change Order No. 3 to the construction contract for the Desert Acceptance Waste Water Collection System, in order to accommodate needed changes during the construction to extend the performance date by 91 days. Additional funds in the amount of $375,890 are already built into the contingency budget for the project. No county funds required. Funding is available in EP-SQDANWAST-CONSTRUCTION.  (Contract No. 2019-0648)
Background:

The County of El Paso received a grant in the amount of $5,193,000.00 and a loan in the amount of $1,334,000.00 to construct first-time wastewater collection system within the Desert Acceptance (Square Dance) area. 

On April 9th 2017, the County received sealed bids to enter into a contractual agreement with Danny Sander Construction to conduct the required work to construct the sewer system within the Square Dance area.

During the construction, the contractor encountered some unforeseen challenges that required changes to the existing design, materials and quantities of the material.

These ten (10) changes are listed on the enclosed change order request. Some of the changes are quantity adjustments that resulted in   contract credit and others were additional items that the contractor encountered which required additional materials and time.

Substantial completion is scheduled to take place on September 18, 2019.

The staff along with the Engineering firm analyzed the proposed change order and concurred with it.


Fiscal Impact:

$375,890.

Contract Price incorporating the Change Order is now $5,153,754.03.


Funding is available in:

 

EP-SQDANWAST-CONSTRUCTION

COEP-5511-0000000-431-80-80000-0001-00000-750003-

Recommendation:Approve and authorize the County Judge to sign the Final Change Order No. 3 to the construction contract for the Desert Acceptance Waste Water Collection System, in order to accommodate needed changes during the construction to extend the performance date by 91 days. Additional funds in the amount of $375,890 are already built into the contingency budget for the project. No county funds required. Funding is available in EP-SQDANWAST-CONSTRUCTION.  (Contract No. 2019-0648)
Prior Action:

April 9th, 2018- Item 15. KK- 2018-0172 Construction Contract with Danny Sander Construction Inc. executed on April 10, 2018, at the same time that all related USDA documents were signed and finalized.

June 4th, 2018 – Item 20, KK 2018-0301. Approve the county judge to sign change order number 1

March 11, 2019- Item 23, KK 2019-0147). Approve and authorize the county judge to sign change order No.2

Strategic Plan:..
Strategic Plan Information:

ATTACHMENTS: