Item Title: | Public Works-Facilities- Replacement of two liebert units at MDR |
Submitted By: | Norma R. Palacios, Director, Public Works Department (915) 546-2015 |
Subject: | Approve and authorize the County Judge to sign the Construction Contract between El Paso County and Trane U.S. Inc. for the replacement of two air conditioning Liebert units in the ITD Server room in the amount of $243,364.89. Funding is available in CIP18-ITD-IT EQUIPMENT. (Contract No. 2019-0185) |
Background: | This contract is to replace two outdated Liebert units in the ITD server room located in the MDR building.
|
Fiscal Impact: | $243,364.89
CIP18-ITD-IT EQUIPMENT
COCP-3001-CIP2018-431-10-11140-0001-IT100-709001-
|
Recommendation: | Approve |