Item Coversheet

County of El Paso
Agenda Item Details


 

Item Title:Public Works - Contract No. 2018-0512 Amendment No. 2 for engineering services for the Square Dance new wastewater collection system
Submitted By:Norma R. Palacios, Director, Public Works Department (915) 546-2015
Subject:Approve and authorize the County Judge to sign the Amendment To Owner-Engineer Agreement Amendment No. 2 with Moreno Cardenas Inc. for additional engineering services provided for the Square Dance (Desert Acceptance Subdivision) new wastewater collection system in the amount of $46,880 paid from USDA-RD Grant Funds.  Funds are available in EP-SQDANWAST-PROF SVC-ENGINRNG.  (Contract No. 2018-0512)
Background:

The County of El Paso received grant in the amount of $7,193,000 and loan in the amount of $1,334,000 secured by certificate of obligation backed by ad valorem taxes to construct first-time wastewater collection system within the Desert Acceptance (Square Dance) area.

On September 8th, 2014 (Item 4-AB), the county entered in contractual agreement with Moreno Cardenas Inc. (MCi) to start required work needed to proceed with the wastewater project. The firm completed the required tasks and submitted the required documentation to USDA-RD for review and approval. After completing the design and specification documents, we encountered few challenges in acquiring an easement and due to that, the engineer was asked to amend the design specifications to accommodate some changes. Moreno Cardenas Inc (Engineer) provided additional services in support of Owner to facilitate newly determined easement acquisitions that were necessary for the Project. Additional easement acquisition support and engineering services were required following Amendment No. 1 from July 25, 2017 through resolution of final easements needed in order to proceed to contract award on March 19, 2018. Additional services included providing coordination and supplemental engineering design support to include: development of multiple maps/exhibits, attending multiple meetings with/for property owners/negotiations, coordination and attending multiple meetings with Owner, coordination with USDA staff to provide project updates, and facilitating Owner final easement development and negotiations process for acquisition of multiple easements through the Tres Suenos Development property limits. In support and as requested, Engineer completed engineering evaluations and assessments of existing offsite lift station infrastructure to facilitate easement negotiations and alleviate concerns that proposed Desert Acceptance wastewater infrastructure would impact future development Engineer prepared a technical memorandum for Owner use in negotiations and presented/clarified findings with developer and their engineer. Engineer coordinated with land developer's engineer to incorporate new development designs into the Desert Acceptance Wastewater design. Modified street alignments and grades were updated into nine (9) design plan sheet revisions and ultimately coordinated to gain final developer acceptance in order to finalize easement approvals.

 

Engineer then prepared the required legal descriptions for Owner use in final easement acquisition.

Fiscal Impact:

$46,880 Paid through USDA-RD Grant Funds

 

EP-SQDANWAST-PROF SVC-ENGINRNG

 

COEP-5515-0000000-431-80-80000-0001-00000-601105-

Recommendation:Approve and authorize the County Judge to sign the Amendment To Owner-Engineer Agreement Amendment No. 2 with Moreno Cardenas Inc. for additional engineering services provided for the Square Dance (Desert Acceptance Subdivision) new wastewater collection system in the amount of $46,880 paid from USDA-RD Grant Funds.  Funds are available in EP-SQDANWAST-PROF SVC-ENGINRNG.  (Contract No. 2018-0512)
Prior Action:

6/4/2018 item 20. Authorize the County Judge to sign change order No.1 KK-2018-0301

4/9/2018 item 15. Approve the County Judge to sign the loan forms, KK-2018-0202

4/9/2018 item 14. Approve the County judge to sign the construction agreement. KK-2018-0172

4/9/2018 item 13. Authorize the County judge to sign amendment 1 to the letter of condition with USDA. KK-2017-0496

8/14/2017 item 3-P. Approve the County judge o sign amendment No.1 with MCI. KK-2017-0496

5/22/2017 item 6. Consider adoption of a resolution of the Commissioners Court of El Paso County, Texas, directing publication of notice of intention to issue combination tax and revenue certificates of obligation and resolving other matters relating to the subject, and authorize the County Judge to sign all necessary documents. 

4/20/2015 item 10. Approve and authorize the County Judge to execute the necessary documents in compliance with USDA Rural Utilities Service condition letter for the Desert Acceptance (Square Dance) First Time Wastewater System Project.

9/8/2014 Item 4-AB, Execute the necessary documents with Moreno Cardenas (MCi)

2/3/2014 item 15. Authorize the Public Works department to proceed with the USDA application


Strategic Plan:..
Strategic Plan Information:

ATTACHMENTS:
DescriptionUpload Date
Amendment no. 29/11/2018